Turap Longsor di Cililitan Mulai Diperbaiki

Collapsed Sheet Pile in Cililitan Being Repaired

Eigth personnel of the Kramat Jati Water Resources (SDA) Task Force, East Jakarta has started to repair the collapsed sheet pile of the crossing channel on Jalan Al Hidayah, RT 01/03 Cililitan Urban Village. The repair has been carried out since Monday (10/9).

It is targeted for completion next week

Kramat Jati Sub-district SDA Executing Unit Head, Muklis expressed the collapse was occurred up to six meters and 2.1 meters. Even at the sheet pile, there was a gaping hole three meters long and two meters deep.

"The repair is done manually. The work progress has touched 20 percent so far. It is targeted for completion next week," he said, Thursday (10/12).

Channel in Cempaka Putih Timur Repaired

He explained the channel along Jalan Swadaya is an access link for the residential area of RT 01/03 Cililitan to Jalan Raya Cililitan Besar or to PGC.

Previously, residents built this place independently in 1986. It was right behind the Environmental Agency office and flanked on the east side by the Jagorawi Toll Road.

"We repair it using river stones to get solid results," he stated.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2378 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1027 personAldi Geri Lumban Tobing
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye986 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye855 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye746 personBudhi Firmansyah Surapati